Resource optimisation for successful project outcomes

Patrick Weaver
December 14, 2011

Current critical path method (CPM) scheduling fails to deliver successful project outcomes, in part because the automatic resource levelling systems in most tools, most of the time, produce sub-optimal results and changing a few settings in any of the tools can produce wildly different outcomes.

Projects achieve completion if the optimum use is made of the critical resources and the flow of work is harmonised. This was the primary focus of Henry Gantt’s work when he developed his famous Gantt chart and it was also the mission of Kelley and Walker when they developed the original CPM system.

For a number of reasons, these original endeavours were ‘dumbed down’ to the current focus on tasks, durations and logic. A resource optimised approach to scheduling involves using the power of modern computers would focus on making the most efficient use of resources to achieve the optimum project completion date. Unfortunately, this is nearly impossible with our current set of scheduling tools.

There are two solutions to this problem: one is to move to a proper resource optimisation approach; the second is to adopt a more pragmatic approach to planning based on scheduling what you know.

Adopting a resource optimisation approach would involve changing the underlying philosophical approach embedded in CPM from a belief that the pre-determined duration and sequencing of activities takes precedence to one that recognises that the real objective of scheduling is to keep the resources working effectively and that any activity sequencing represents a constraint on the locations where resources can work.

A new paradigm?

This change in approach would represent a totally new paradigm in the modern age, although as mentioned above the original objective of CPM was resource optimisation! CPM was dumbed down to its current form to achieve realistic processing times on the computers available in the late 1950s; unfortunately almost no one has moved on from these basic structures for a CPM model despite the massive advances in computer power.

A resource optimisation model would result in:

  • Recognising that activities are variable. Any division of work into activities is arbitrary and can be changed.
  • Durations are a consequence of both the quantity and quality of resources actually assigned to the work. The relationship is complex (not simplistic resource driven durations) and capable of optimisation based on the project objectives.
  • Resource workflows are the core determinant of project outcomes. Optimising resource workflows minimises cost and time outcomes. Sub-optimal or disrupted workflows increase cost and time outcomes.

An alternative and probably more realistically achievable approach in the short term, can be summarised as ‘plan what you know and budget the rest’. This is the approach adopted in the Chartered Institute of Building’s Guide to good practice in the management of time in Complex Projects. The guide introduces the concept of schedule density:

  • Work more than 12 months in the future is planned at low density and defines the long-term strategic commitments of the project.
  • In the near term, work more than three months in the future is scheduled at medium density and defines the tactical approach to achieving the overall strategy set out in the low density schedule.
  • Work in next three months is scheduled at high density and defines in detail who will be doing what, where and when based on the resources actually available and their measured productivity.

The new paradigms proposed in this article are the focus of ongoing work to formulate a practical set of proposals that may help make scheduling more useful and effective.

However, to be effective, a significant cultural change will be required that moves people’s focus from ‘the contract schedule’ and the associated fighting over delay, disruption and extensions of time, to a focus on delivering the contract on schedule! Watch this space.

Author avatar
Patrick Weaver
Patrick Weaver is the managing director of Mosaic Project Services and the business manager of Stakeholder Management Pty Ltd. He has been a member of both PMI and AIPM since 1986 and is a member of the Asia Pacific Forum of the Chartered Institute of Building. In addition to his work on ISO 21500, he has contributed to a range of standards developments with PMI, CIOB and AIPM.